针对丹东电厂2台350 MW汽轮机主汽阀卡涩现象,分析了主汽阀卡涩的原因,采取了相应的防范措施后,解决了主汽阀卡涩问题。
Directing against the unsmooth blockage phenomenon appeared on main steam valves of two 350 MW steam turbines manufactured by The Westing house Corporation, the causes leading to said blockage have been analysed. After adopting corresponding preventive measures, the said blockage troubles have never occurred again.
出处
《热力发电》
CAS
北大核心
2007年第1期99-100,共2页
Thermal Power Generation
关键词
汽轮机
主汽阀
联合汽阀
卡涩
steam turbine
main steam valve
combined regulating valve
unsmooth blockage