基于约束满足的车间调度算法综述 被引量:34

Constraint-based algorithm for Job Shop scheduling
下载PDF
导出
摘要 为了说明如何利用启发式信息构造车间调度的约束满足求解算法,首先概述了常规约束满足求解技术,进而介绍了车间调度问题的约束传播算法、树搜索算法和启发式修复算法的构造原理及适用性。在此基础上,针对目标优化问题,给出两种求解框架。最后,指出近期的研究趋势和进一步的研究工作。 To explain how to use the heuristics information of the problem to construct constraint-based solving algorithm, the general constraint satisfaction solving technology was briefly introduced, then the principles and the applicability of constraint propagation algorithm, tree search algorithm and heuristics repair algorithm for Job Shop scheduling were summarized. Furthermore, two solution frameworks for objective function optimization problem were given. Finally, the research trend of constraint-based scheduling algorithm was pointed out and the prospective research was also proposed.
出处 《计算机集成制造系统》 EI CSCD 北大核心 2007年第1期117-125,共9页 Computer Integrated Manufacturing Systems
基金 国家自然科学基金资助项目(70371057)。~~
关键词 车间调度 约束满足 约束传播算法 树搜索算法 启发式修复算法 混合求解方法 Job Shop scheduling constraint satisfaction constraint propagation algorithm tree search algorithm heuristic repair algorithm hybrid solution method
  • 相关文献

参考文献35

  • 1FOX M S,SMITH S F.ISIS-a knowledge-based system for factory scheduling[J].Expert Systems,1984,1(1):2549.
  • 2段黎明,陈进,刘飞.基于约束分析的 Job Shop 调度算法的综述[J].重庆大学学报(自然科学版),1998,21(1):133-138. 被引量:11
  • 3陈恩红,薛瀚宏.基于约束满足的Job-Shop调度问题求解方法研究[J].软件学报,1998,9(12):946-948. 被引量:13
  • 4杨宏安,孙树栋,王荪馨,柴永生.基于CSP的Job shop调度算法研究[J].系统工程,2004,22(11):15-18. 被引量:9
  • 5杨宏安,孙树栋,王荪馨,吴秀丽.基于约束满足的Job-Shop调度算法研究[J].计算机工程与应用,2003,39(31):36-37. 被引量:11
  • 6BRALSFORD S C,POTTS C N,SMITH B M.Invited review:constraint satisfaction problems:algorithms and applications[J].European Journal of Operational Research,1999,119(3):57-581.
  • 7CESTA A,ODDI A,SMITH S F.A constrained-based method for project scheduling with time windows[J].Journal of Heuristics,2002,8(1):109-136.
  • 8MINTON S,JOHNSTON M D,PHILIPS A B,et al.Minimizing conflicts:a heuristic repair method for constraint satisfaction and scheduling problems[J].Artificial Intelligence,1992,58(1-3):161-205.
  • 9BAPTISTE P,LEPAPE C.A theoretical and experimental comparison of constraint propagation techniques for disjunctive scheduling[C]//Proceedings of the 14th International Joint Conference on Artificial Intelligence.San Francisco,Cal.,USA:Morgan Kaufmann,1995:600-606.
  • 10CHENG C,SMITH S F.Applying constraint satisfaction techniques to Job Shop scheduling[J].Annals of Operations Research,1997,70(1):327-357.

二级参考文献27

  • 1Bartak R.Constraint Programming:A Survey of Solving Technology[J]. AIRONews journal ,Italy, 1999;4(4).
  • 2Bartak R.Constraint Programming:What is behind?[C].In:Proceedings of CPDC99 Workshop,Gliwice, 1999-06.
  • 3Bartak R.Constraint-Based Scheduling:An Introduction for Newcomers[R].Technical Report TR 2002/2,Department of Theoretical Computer Science and Mathematical Logic,Charles University,2002.
  • 4Dechter R.Network-based heuristics for constraint satisfaction problem[J].Artificial Intelligence, 1987 ;34.
  • 5Philippe Baptiste,Le Pape.Constraint-Based Optimization and Approximation for Job Shop Scheduling[C].In:Proceedings of the AAAISIGMAN Workshop on Intelligent Manufacturing Systems,IJCAI-95, Montreal, Canada, 1995.
  • 6刘飞,制造系统工程,1995年
  • 7Tang L, Liu J, Rong A, et al. A mathematical programming modelfor scheduling steelmaking-continuous casting production [ J ].European Journal of Operational Research, 2000, 120(2) : 423-435.
  • 8Harjunkoski I, Grossmann I E. A decomposition approach for the scheduling of a steel plant production [ J]. Computers and Chemical Engineering, 2001,25( 11 - 12) : 1647-1660.
  • 9Pacciarelli D, Pranzo M. Production scheduling in a steelmaking-continuous casting plant [ J]. Computers and Chemical Engineering, 2004, 28(12) : 2823 -2835.
  • 10Dechter R, Frost D. Backjump-based backtracking for constraint satisfaction problems [ J ]. Artificial Intelligence, 2002, 136(2) : 147 -188.

共引文献37

同被引文献325

引证文献34

二级引证文献120

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部