针对寺河矿东风井35 kV变电所在生产中显现出环节能力严重不足的问题,介绍了该变电所的现状、主要存在问题及改造方案,通过详细对比阐述了三个改造方案的优缺点,最后得出了合理可行的方案,对煤矿供电的设计、运行、管理有一定的参考作用。
In light of the problem of insufficient power of 35 kV transformer station of east ventilation shaft in Sihe coal mine in the production, this paper introduces existing conditions, main problems and reconstruction schemes of the transformer station, illustrates advantages and disadvantages of three reconstruction schemes by comparison, and gets the rational and feasible scheme, which has a certain referential functions for the design, operation and management of power supply in coal mine.
出处
《山西建筑》
2007年第4期209-211,共3页
Shanxi Architecture
关键词
供电系统
改造方案
供电质量
线路损耗
power supply system, reconstruction scheme, power supply quality, line loss