摘要 对攀钢炼铁厂1、2号高炉进出物料进行了系统取样,测定了样品的w(Zn),结合高炉生产数据对1、2号高炉做了锌平衡计算。结果表明:在高炉冶炼稳定的条件下,进出高炉的锌总量基本平衡;瓦斯泥未经处理直接配入烧结是造成入炉原料锌负荷高的主要原因;高炉内的锌主要由煤气中的粉尘带出,而通过渣铁带出的锌量可以忽略。 Based on systematic sampling and chemical analysis, zink balance is calculated for Pansteel's No. 1 BF and No. 2 BF. The results show that the total zinc amount entering into the blast furnaces is nearly balanced with the overflowing amount of zink in stable operation conditions; the higher zinc amount is caused due to adding sludge that is not dezinced before mixed with sintering charge; zinc removal from the blast furnaces is mainly by the dust of top gas and the zinc removal amount by slag and hot metal can be negligible.
出处 《钢铁研究》 CAS 2007年第1期9-11,26,共4页 Research on Iron and Steel
关键词 高炉 w(Zn) 锌平衡 污泥 blast furnace w(Zn) zinc balance sludge
  • 相关文献

参考文献6

二级参考文献3

  • 1[2]Gladyshev V I, Filippov V V, Rudin V S. Influence of Zinc on the Life of the Hearth Lining and Blast-furnace Operation. Steel in Translation, 2001,31(1):1~4.
  • 2[5]Hafez A I,Elmanharawy M S,Abdel Fattah M A. Chemical Treatment of the Water Used in the Blast Furnace Gas Cleaning Cyclein the Egyptian Iron and Steel Company. International Journal of Environment and Pollution,2002,12(4):359~371.
  • 3[6]Shchukin Yu P, Sedinkin V I,Polushkin M E. Removal of Blast-furnace Sludge with High Zinc Content from Recycling. Steel in Translation ,1999,29(11):6~8.

共引文献105

同被引文献226

引证文献9

二级引证文献104

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部