以华润电厂一期工程冷却塔为例,介绍了采用在平桥标准节上加装泵管,由拖泵进行混凝土垂直运输和浇筑的方案。实施该工艺后,在未加大成本的前提下,提高筒壁施工速度35%,缩短工期17天。
Taking Huarun plant phase one project cooling tower construction as an example, this paper introduces the scheme of adding pumping pipe to standard flat bridge to vertically transport and pour concrete with tractive pump. Having adopted such technique, the tower wall construction speed was increased by 35% and the construction time was reduced by 17 days without increasing costs.
出处
《电力建设》
2007年第2期56-57,共2页
Electric Power Construction
关键词
冷却塔
平桥
拖泵
cooling tower, flat bridge, tractive pump