摘要
水流经过水闸、溢流坝等水工建筑物,下游消能有时需要采用综合式消力池方案,笔者在研究单纯确定池深和坎高的基础上,导出计算综合式消力池的迭代公式,使得计算方便,而且精度能够保证。
When water flow passes through the hydraulic structures such as sluice or spillway dam,the plan of comprehensive stilling basin is sometimes adopted for dissipating energy.In this paper,on the basis of author's research result to determine basin depth or barrier height of stilling basin solely, the iteration formulas to calculate comprehensive stilling basin are introduced.The calculation of this method is convenient and its calculation accuracy can be ensured.
出处
《山西水利科技》
2007年第1期56-57,66,共3页
Shanxi Hydrotechnics
关键词
综合式消力池
简便计算
迭代
comprehensive stilling basin simple calculation iteration