该文对杨柳青电厂300MW供热式汽轮机的中.低压缸分缸压力的选择进行了分析,指出其不合理之处,并提出了合理确定分缸压力的建议.
Abstract The paper discusses the pressure split between the IP and LP cylinder of Yangliuqing Power Plant's 300 MW cogeneration steam turbine,points out the irrationality of the choice and recommends a more reasonable way of making a decision on the split.