摘要
介绍了靖远第二发电有限公司300 MW机组简况,锅炉启动点火前的3种上水方式及相关操作。分析了启动过程中存在的一些问题,并提出了系统改造的一些建议和操作中的注意事项。
An introduction is being presented to the general condition of Jinyuan No.2 Power Co. Ltd's 300 MW power unit, its 3 way of boiler water feeding prior to ignition as well as relevant manipulation procedures. A number of problems encountered during start-up are analyzed while some suggestions for system's retrofit and noteworthy items that need to be cared during operation proposed.
出处
《发电设备》
2007年第2期128-132,共5页
Power Equipment
关键词
能源与动力工程
锅炉
启动
上水
加热
改进
energy and power engineering
boiler
start-up
water feeding
heating
improvement