巧用脚手架加快工程进度的方法

USING SCAFFOLDS WITH GOOD FLEXIBILITY CAN CHANGE CONSTRUCTION SEQUENCE AND ACCELERATE CONSTRUCTION PROGRESS
下载PDF
导出
摘要 在某大型商场的正立面改造扩建工程中,巧妙搭设外承重脚手架,改变了常规的施工顺序,将传统的从下至上依次施工变为多层钢筋、模板立体施工,因不需要下一层混凝土施工完毕便可进行上一层的模板支撑、梁植筋、钢筋绑扎的施工,从而缩短混凝土浇筑的间隔时间,达到加快进度的目的。 Outside in some large -scale market transformation extension project, the load-bearing scaffold was ingeniously pnt up, changed the conventional construction order, turning the traditional from under into the multilayered steel bar, the template three-dimensional construction. Because it does not need the next concrete construction to finish they then may carry on the construction on a template strut, the steel bar binds, thus reduces the concrete casting time interval to achieve the goal of speeding up the progress.
出处 《武汉工业学院学报》 CAS 2007年第1期82-85,共4页 Journal of Wuhan Polytechnic University
关键词 外承重脚手架 施工 混凝土 outside load - bearing scaffold construction concrete
  • 相关文献

参考文献2

  • 1廖代广.建筑施工技术[M].武汉:武汉工业大学出版社,2003.
  • 2JGG130 20010,建筑施工扣件式钢管脚手架安全技术规范[S].

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部