摘要
结合华电国际邹县发电厂四期工程2×1000MW超超临界机组在设计及设备选型阶段的工程实践,对选用双列高加布置方案或单列高加布置方案的利弊进行了详细的论述,所述内容应对以后的超超临界机组的系统设计有所借鉴作用。
With the engineering practice of 2 × 1000MW ultra - supercritical unit of Stage 4 Project of HDPI Zouxian Power Plant at the period of equipment designing and selecting, the advantages and disadvantages of two - row arrangement scheme and single - row arrangement scheme of the high - pressure heaters are discussed in detail. All the illustration in this paper probably can be used for reference of the later system design of ultra - Supercritical unit.
出处
《山东电力技术》
2007年第1期30-33,共4页
Shandong Electric Power
关键词
超超临界
1000MW
高加
设计
ultra- supercritical unit
1000MW
higher pressure heater
design