根据湛江海湾大桥连接线一期工程某些填方路段出现龟裂的情况,进行了试验分析并提出了相应措施。
According to the situation that the map cracking appears in some fill section in the first stage construction of the connecting line of bay bridge in Zhanjiang City, this paper makes the experimental analysis on it and advances some corresponding measures.
出处
《科技情报开发与经济》
2007年第6期F0003-F0003,F0004,共2页
Sci-Tech Information Development & Economy
关键词
路基龟裂
路基填土
连续施工工艺
map cracking of subgrade
subgrade fdl