结合马嘎车站站场改造实例,详细介绍站场改造的技术准备、施工方案、缩短封锁时间技巧、道岔整修,确保在封锁时间内完成施工任务,为今后站场改造施工组织提供借鉴。
Combining with the reconstruction of Mage station site, the technical preparation, the construction scheme, the skill of shortening the closed time and the switches' refurbishment of the reconstruction are introduced. They can be taken as a reference for the construction organization of site reconstruction.