大跨度小净距群洞隧道施工方案优化研究 被引量:22

Optimization Analysis of Construction Schemes for Large Span and Small Clear Distance Group Tunnels
下载PDF
导出
摘要 上海国际航运中心洋山深水港区小洋山隧道工程为国内第一座小净距大跨度群洞隧道,对其进行施工方案优化分析有重大理论与实际意义。作者选择了三种不同施工顺序工况进行有限元数值模拟分析,对比各工况屈服度云图、最危险阶段受影响最大的隧道衬砌上的弯矩和竖直位移的增量值,以此为准则,得出最合理的施工顺序,并在这基础上计算了隧道不同间距对群洞隧道的影响。从施工顺序和合理间距两方面进行数值分析,从而使得实际隧道施工方案得到优化。 The small Yangsan Tunnel of Shanghai international shipping center Yangsan deep-water port area is the first small clear distanee and large span group tunnels in our country. The optimization analysis of construction schemes for this tunnel has important theoretical and practical meaning. The authors have selected three operating models for finite element simulation analysis. By comparing the yielding degree around the tunnels, the moment and the vertical displacement of lining in the most dangerous tunnel, the optimal construction scheme can be obtained. This paper also studies the influence of different distance to group tunnels. Based on analysis on the two aspects as construction sequence and proper distance , the practical construction scheme is optimized.
出处 《地下空间与工程学报》 CSCD 2007年第1期96-100,共5页 Chinese Journal of Underground Space and Engineering
关键词 群洞 衬砌 施工顺序 屈服度 合理间距 group tunnels lining construction sequence yielding degree proper distance
  • 相关文献

参考文献7

二级参考文献8

  • 1中隧集团二处有限责任公司.广州地铁越秀公园站竣工资料[Z].,2002..
  • 2中铁隧道勘测设计院 广州地下铁道设计研究院.广州地铁越秀公园站施工设计[Z].,2001..
  • 3谢谟文,武汉水利电力大学学报,1994年,8期,35页
  • 4谢谟文,人民长江,1992年,6期,45页
  • 5赵代深,水利学报,1988年,6期
  • 6交通部发布《公路工程技术标准》[J]石油沥青,2004(02).
  • 7JTJ 042-1994.公路隧道施工技术规范(附条文说明)[S],1994.
  • 8JTG B01-2003.公路工程技术标准[S],2004.

共引文献113

同被引文献200

引证文献22

二级引证文献97

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部