SMW工法设计与施工关键技术难点研究 被引量:15

Study of Some Key Technical Issues in the Design and Construction of SMW Method
下载PDF
导出
摘要 南京地铁工程地下二层车站基坑的开挖深度一般为15—17米,大大超出了国内以往用SMW工法施工的基坑工程,可以借鉴的成功经验较少.为解决SMW工法在南京地铁软土深大基坑中的关键技术问题,通过采用室内试验、现场实测及数值分析等多种方法对型铜——水泥土组合结构工作机理进行综合研究,提出了SMW工法应用于基坑工程的设计理论和计算方法.SMW工法在南京地铁一、二号线工程中的成功实践,创造了SMW工法在我国深基坑工程应用中开挖最深的记录. The excavation depth of the two-story underground station of Nanjing's subway system is generally between 15 and 17 meters, which greatly exceeds the depth of earlier projects using SMW method in China, therefore there is little experience for reference. In order to solve the key technical problems in the utilization of SMW method in the construction of the deep foundation pit in soft soil, the mechanism of the section steel- cement soil composite structure is studied through laboratory experiments, field tests and numerical analysis, and the design theory and calculation method of the utilization of SMW method in foundation pit projects are also advanced. The successful practice of SMW method in the projects of Nanjing's Line 1 and Line2 subway set the record as China's deepest excavation depth in the deep foundation pit construction projects using SMW method.
作者 徐源 XU Yuan (Nanjing Metro Corporation, Nanjing 210000, China)
出处 《徐州工程学院学报》 2007年第2期37-42,共6页 Journal of Xuzhou Istitute of Technology
关键词 地铁 深基坑 SMW工法 组合刚度 H型钢 metro deep foundation pit SMW method combined stiffness H- steel
  • 相关文献

参考文献3

二级参考文献16

共引文献93

同被引文献60

引证文献15

二级引证文献32

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部