软弱地基上5万m^3油罐地基处理方案选择 被引量:8

Foundation Design of 5×10~4 m^3 Oil Storage Tank Situated on Soft Foundation
下载PDF
导出
摘要 通过介绍天津南疆建造5万m3大型油罐地基处理方案的选择过程,从适用条件、施工方法、经济效益方面分析了预制桩、普通灌注桩、柱锤夯扩桩处理大型油罐地基的优缺点,探讨了在软弱地基上建造大型油罐地基的处理方法。根据天津南疆的具体情况,最终选用了预制桩、柱锤夯扩桩相结合的方案,取得了良好的效果,油罐投入运行两年多,基础沉降仅为93mm。 This paper introduces the scenario selection course of foundation treatment of a 5×104 m3 large scale oil storage tank in Nanjiang, Tianjin. Advantages and disadvantages of precast piles, usual drilled and grouted piles and column-hammer compacted-expended piles used to strengthen foundation of large scale oil tank are analyzed in respects of applicable conditions, construction methods and economic benefits. The foundation treatment methods of large tanks built on soft foundations are discussed. According to the practical situation of Nanjiang, the combined scenario of precast piles with column-hammer compacted-expended piles was finally chosen and achieved good results.
作者 吴峤
出处 《石油工程建设》 2007年第2期50-52,共3页 Petroleum Engineering Construction
关键词 软弱地基 大型油罐 地基处理 soft foundation large scale oil storage tank foundation treatment
  • 相关文献

参考文献4

  • 1JGJ94-1994.建筑桩基技术规范[S].[S].,..
  • 2JGJ/T135-2001.复合载体夯扩桩设计规程[S].[S].,..
  • 3GB50007-2002.建筑地基基础设计规范[S].[S].,..
  • 4SH 3068-1995,石油化工企业钢储罐地基与基础设计规范[S].

共引文献1848

同被引文献16

引证文献8

二级引证文献8

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部