摘要
大连中远30万t浮船坞工程是目前国内最大的浮船坞工程,共设计海上基桩30根,桩径800mm,嵌入中风化岩石4~5m,最深达8m。利用驳船进行海上基桩施工,采用FGC-15D型大直径湿式反循环潜孔锤钻进成孔,满足施工工艺和工期要求。
Dalian COSCO 300000 DWT floating dock is the largest floating dock engineering in China at present, with 30 sea piles of 800 mm in diameter, embedded 4 ~5m (the deepest is up to 8 m) in intermediary weathering rock. Barge was used in sea pile construction, and FGC - 15D large diameter wet reverse circulation DTH was adopted for hole completion.
出处
《探矿工程(岩土钻掘工程)》
2007年第4期6-8,11,共4页
Exploration Engineering:Rock & Soil Drilling and Tunneling