期刊文献+

平顶山二电厂向华中电网送电规划研究 被引量:2

Research on Power Transmission Planning from Pingdingshan No. 2 Power Plant to Central China Power Grid
下载PDF
导出
摘要 “十二五”期间平顶山二电厂将建设4台1GW超超临界燃煤机组,为保证电厂电力的外送,促进电网与电源的协调发展,文章进行了平顶山二电厂向华中电网送电的输电规划研究,重点研究了华中东部四省市场空间、电厂向华中东部四省送电的必要性及输电方案,通过对各输电方案的综合技术经济比较提出了推荐方案。 In the period of the 12th five-year plan, four ultra-supercritical coal-fired 1 GW units will be built in Pingdingshan No. 2 power plant. To ensure successful power transmission outwards after the building-up of the four ultra-supercrifical units and to promote the coordinative development between power grid and power source, the power transmission planning from Pingdingshan No. 2 power plant to Central China power grid is researched. In this research the electricity market space of four provinces in Central China, the necessity of transmitting power from Pingdingshan No. 2 power plant to these four provinces and corresponding power transmission planning are emphatically explored. By means of comprehensive techno-economic comparison of different power transmission schemes, the recommended power transmission scheme is presented.
机构地区 中南电力设计院
出处 《电网技术》 EI CSCD 北大核心 2007年第8期52-57,共6页 Power System Technology
关键词 电力市场 输电方案 超超临界燃煤机组 华中电网 平项山二电厂 electricity market transmission scheme ultra-supercritical coal-fired units Central China power grid Pingdingshan No. 2 power plant
  • 相关文献

参考文献18

二级参考文献98

共引文献221

同被引文献11

引证文献2

二级引证文献8

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部