摘要
由于人们质量意识的提高,对钢筋混凝土框架结构表面质量已上升到追求镜面效果的高度,生产镜面混凝土的能力以及镜面实施效果能充分体现一个施工企业的市场竞争实力。施工钢筋混凝土框架的镜面效果主要由模板工艺来体现。国电宣威发电有限公司6×300MW工程钢筋混凝土框架结构中(五、六、七期)广泛应用镜面混凝土施工工艺,成功生产出镜面混凝土,工艺质量及效果明显。
Because of increasing awareness of quality, the pursuit of reinforced concrete frame finishing quality has reached such a high level that mirror finish is desired. The capabilities of mirror concrete manufacturing and construction reflect the marketing competition strength of a construction company. The key to the mirror surface concrete in reinforced concrete frame construction depends on the moulds. In the frame construction of Guodian Xuanwei Power Plant 6×300 MW project (phases 5, 6 and 7 ), the mirror surface concrete construction technique was widely used, mirror surface concrete was successfully manufactured, and the quality is very impressive.
出处
《电力建设》
2007年第5期69-73,共5页
Electric Power Construction
关键词
钢筋混凝土框架结构
施工工艺
镜面混凝土
模板
reinforced concrete frame
construction technique
mirror surface concrete
mould