摘要 当单桩静载试验存在较长的非有效段时,需要采取有效措施去除非有效段桩侧摩阻力,以求得在实际工作标高上的单桩承载特性。结合北京地区某工程测试实例,说明通过双套筒法可以有效地去除非有效段桩侧摩阻力,并与实际工程桩的测试结果进行对照分析,表明直接应用试桩结果存在一定风险,需要在实际工程设计的应用中考虑上覆土层对测试结果的影响。 In pile static load test, effectual isolation method must be adopted to wipe off the unemployed segment pile shaft resistance in order to get the bearing characteristics of a single pile at the actual working elevation, when there is a relatively long unemployed pile segment. It is illustrated with an engineering test example in Beijing that double steel casing method is an efficient way to wipe off the unemployed segment pile shaft resistance. Farther, by comparing the tested result of the work pile, it shows that there will be a risk in directly applying the test result data in project, and the effect of overburden on thee test results should be considered in pile foundation design.
出处 《工业建筑》 CSCD 北大核心 2007年第4期22-24,共3页 Industrial Construction
关键词 静载试验 侧阻力 双套筒 桩基 static load test pile shaft resistance double steel casing method pile foundaiton
  • 相关文献

参考文献1

  • 1JGJ94-94.建筑桩基技术规范.[S].,..

共引文献149

同被引文献4

引证文献3

二级引证文献5

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部