摘要
研究目的:跨既有铁路的施工在我国当前铁路建设中占有很大的比例。兰武二线古浪河大桥横跨既有铁路,本文通过对此桥32 m结合梁施工实例的介绍,为类似工程的施工提供经验。研究结果:在兰武二线古浪河大桥的结合梁施工中,采用相应的施工方案,使工程建设安全可靠,顺利完成。研究结论:既有线桥梁施工中施工方法的选择、施工步骤的确定及现场的施工组织和安全管理必须规范,方能取得良好效果。
Research purposes: The construction of works across existing railway lines takes up a significant proportion of the current railway construction in China. This paper introduces the case of construction of 32 m composite girder of Gulang River Bridge on the second line of Lanzhou - Wuwei Railway across the existing railway line to give more experiences to other similar works in construction.
Research results: In the construction of composite girders of Gulang River Bridge on the second line of Lanzhou - Wuwei Railway, the corresponding construction proposal is adopted to ensure the safe, reliable and successful construction of this project.
Research conclusions: The selection of construction methods, determination of construction procedures, on - site construction organization and safety control for bridges across existing lines must be standardized so as to get good effects.
出处
《铁道工程学报》
EI
北大核心
2007年第4期39-42,60,共5页
Journal of Railway Engineering Society
关键词
铁路
结合梁
既有线
施工
railway
composite girder
existing railway line
construction