通过对广东抽水蓄能电站一期、二期和浙江天荒坪抽水蓄能电站SFC系统特点的分析总结,以及在安装和调试中遇到的问题和解决办法的介绍,可为今后大力发展我国抽水蓄能电站工程建设提供参考。
Based on the studies made on the characteristics of the SFC system of the 1st and 2nd stage works of the Guangdong pumped storage power stations and that of the Tianhuangping pumped storage power station, as well as on the description of experiences in problem-tackling in the erection and testing of these projects, the paper provides references for future pumped storage projects in China
出处
《水力发电》
北大核心
2007年第5期51-54,85,共5页
Water Power
关键词
SFC
全控桥
转子初始位置
起动原理
抽水蓄能电站
SFC (Static Frequency Convertor)
fully controllable bridge
initial position of runner
starting principle
pumped storage power plant