摘要
尾水调压井井筒混凝土滑模施工的核心是合理的结构设计、精准的加工及安装和现场有效的控制措施,这是保证尾水调压井混凝土施工质量的关键。为此,对漫湾水电站二期工程尾水调压井井筒混凝土施工具体问题的处理和解决方法进行了介绍,可供相关工程参考借鉴。
This paper introduces the solving and disposing method in the concrete construction of the well wall of the sure tank of Manwan II project. Its key issues lies in the rational structure designing, precisely manufacturing and installing, and effective local controlling measures All of that provided the linchpin to ensure the concrete construction quality of the sure tank.
出处
《水力发电》
北大核心
2007年第5期75-77,共3页
Water Power
关键词
漫湾二期工程
尾水调压井
滑模设计
滑模施工
Manwan Ⅱ project
surge tank
designing of slip-form
slip-form construction