摘要
从工程变更、施工合同两方面介绍了引起索赔的主要因素,阐述了工程索赔的概念,探讨了工程索赔的技巧,指出工程项目管理人员应合理运用现场条件使用索赔技巧,从而提高经济效益。
From two aspects: project changes and construction contract reasons caused the project claims are introduced as well as the concept of project claim. According to claims skills are discussed. Author points out that mangers should utilize on-site conditions and claim skills to increase economic benefits.
出处
《山西建筑》
2007年第16期267-268,共2页
Shanxi Architecture
关键词
索赔
合同
工程变更
claim, contract, project changes