摘要
本文针对雪峰集团的砂岩矿成品矿仓回填材料使用不当,雨水冲刷造成坍塌,致使排架柱倾斜的事故,通过采用顶压、灌浆等综合措施修复了工程缺陷,取得了很好的效果.本文方法可供解决工程施工过程中的纠偏问题时参考.
For improper refilling materials, the storehouse of Xue Feng Corp for storing finished products of sandrock mines is collapsed by rain pouring, slanting the bent frame column. After the comprehensive measures including top compression and grouting are taken, the construction has been repaired, gaininga profitable effect. This method is also consulted to rectify the errors in the engineering construction.
出处
《南华大学学报(自然科学版)》
2007年第1期59-62,69,共5页
Journal of University of South China:Science and Technology
关键词
排架柱
倾斜
纠偏
顶压
灌浆
bent frame column
slanting
adjustment
top compression
grouting