针对沁北电厂二期600MW给水泵组选型,从给水泵台数、容量、启动备用泵配置及电动给水泵等方面进行技术经济比较,供相关人员探讨和商榷。
We have done the technical and economical comparison from the quantity of the water feed pump, capacity, the disposition of the starting spare pump, and motor-water-feed-pump about the sample of 600MW water feed pump group of the phase 2 engineering project of Qinbei Thermal Power Plant for discussion and deliberation for the concerned specialists.
出处
《河南电力》
2007年第1期48-50,共3页
Henan Electric Power
关键词
给水泵组
容量配置
water feed pump group
capacity and disposition