无锡城北污水处理厂二期工程进水泵工况点计算方法

Working state calculation of inlet pumping station in Chengbei Wastewater Treatment Plant in Wuxi City
下载PDF
导出
摘要 无锡市城北污水处理厂扩建工程因增加水解酸化池预处理单元而需加大进水污水泵扬程,通过合理布置和计算机编程精确求解,以原有低扬程泵和新选高扬程泵运行工况点均在高效区为约束条件,得出原水泵保留,增加2台大泵并联的设计结论,运行工况与理论计算基本吻合。 The lifting head of the inlet pumping station in the designed extend project of Chengbei Wastewater Treatment Plant in Wuxi City has to be increased to compensate the added hydraulic drop at the pre-treatment of anaerobic hydrolysis tank. The layout and parallel working states of pumping assemblies existing and lately-increased are analyzed by computer-aided calculation and adjusted into a restrict condition: all of them are working in the high efficiency range. The result is existing (low pressure) reserved and two (high pressure) added. The practical operation almost confirms the calculation.
出处 《给水排水》 CSCD 北大核心 2007年第6期100-103,共4页 Water & Wastewater Engineering
关键词 并联泵工况点 MATLAB 数解法 Working state of parallel pumping assemblies Matlab Numerical solutions
  • 相关文献

参考文献1

  • 1姜乃昌.水泵与水泵站.北京:中国建筑工业出版社,1993

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部