某特大桥连续刚构箱梁底板修复施工 被引量:2

REPAIR CONSTRUCTION OF BOTTOM SLAB IN A CONTINUOUS FRAME BRIDGE
下载PDF
导出
摘要 某高速公路特大桥,由于施工阶段底板纵向预应力束张拉导致箱梁底板发生层状撕裂,须凿除底板后重新浇筑。修复施工过程中,张拉底板钢束后产生的压应力将从底板向全截面传递,为保证压应力能有效传递,采取了一系列施工措施,保证了结合面的粘结性能和抗剪能力,施工效果良好。 Because of tension of pre-stressed steel bar during construction, the bottom slab of a box girder bridge cracked transversely. And the slab must be removed and recast. After recasting of concrete, pre-stressed steel bar was tensioned again and the compressive stress was transferred from bottom to all cross-section in the repairing process. To ensure the effective transfer of the stress, some measures were taken to guarantee the bonding performance and shear resistance of connecting interface, reaching good construction effect.
出处 《建筑技术》 北大核心 2007年第6期443-445,共3页 Architecture Technology
关键词 桥梁修复施工 箱形梁 界面处理 repair construction of bridge box girder interface treatment
  • 相关文献

参考文献2

  • 1赵志方,周厚贵,袁群,等.新老混凝土界面机理研究与工程应用[M].北京:中国水力水电出版社,2003.
  • 2G James Macgregor. Reinforced Concrete: Mechanics and Design [M].PRETICE HALL, Upper Saddle River, NJ. 1997.

同被引文献9

引证文献2

二级引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部