摘要
在高山峡谷地区修建堆石坝,将正常或非常溢洪道直接布置在坝顶上,具有简化枢纽布置、节约工程造价和方便施工等优点。通过对堆石坝坝顶溢洪道带有地锚的泄槽底板进行稳定分析和内力计算,得出地锚参数与其所受各力之间的关系式和安全系数表达式,为今后的工程设计提供理论计算方法,经实例验证该方法是可行的。
To build the rock-fill dam in the valley between high mountains, the normal or extraordinary spillway is often arranged on the crest of dam directly, which can simplify the control structure arrangement, save project cost and is easy to construct. The stability analysis and stress calculation for the chute bottom slab with anchorage of crest spillway of rockfill dam gives the anchorage parameters, relationship of various forces and its safety coefficient expressions, which provides the theoretical calculation method for the future project design. The practice showed that this method is feasible.
出处
《水力发电》
北大核心
2007年第6期32-34,共3页
Water Power
基金
新疆水利水电重点科学基金资助项目(xjzdxk-2002-10-05)
新疆高校科研计划重点项目基金(xjedu2005Ⅰ09)
新疆高等学校科研计划资助项目(xjedu2004Ⅰ14)
关键词
堆石坝
坝顶溢洪道
泄槽底板
地锚
稳定分析
rockfill dam
crest spillway
chute bottom slab
anchorage
stability analysis