期刊文献+

国家体育馆型钢柱施工测量 被引量:2

Construction Survey of National Stadium Profile Steel Pillar
下载PDF
导出
摘要 采用测量控制的方法来检测调整型钢柱的施工安装.用导线测量以及外控与内控相结合的方法建立平面测量控制网,为高精度细部放样打好基础;采用附合水准路线建立高程控制网.依据控制网和设计轴线建立平面控制格网,在轴线延长线上设立控制点.用两台经纬仪分别架设在引出轴线上,结合水准仪对型钢柱进行测量校正,保证其轴线位置、竖直度及柱顶标高符合设计和规范要求. Survey control technique is used to check and correct the costruction of profile steel pillar in this article. Horizontal control network is first built with traverse survey and the combination of intercontrol and extra-control, which put the way for precise detail loft. Vertical control network is done with the annexed leveling line. Horizontal control grid is built according to the network and design axis and control points are designed on the extended line of axis. Two theodolites are placed on the extended line of axis with the level to check and correct the profile steel pillar and assure the axis position, vertical direction and pillar elevation agree with the design and caritas.
作者 刘健 王国利
出处 《北京建筑工程学院学报》 2007年第2期27-30,共4页 Journal of Beijing Institute of Civil Engineering and Architecture
关键词 型钢结构 施工 测量控制 profiled steel structure construction survey control
  • 相关文献

参考文献4

  • 1中国有色金属工业总公司.GB50026--93工程测量规范[S].北京:中国计划出版社,2001
  • 2鲍广盛.钢结构施工技术及实例[M].北京:中国建筑工业出版社,2005.73—76
  • 3龙正武 秦长利 李九林 等.国家体育场钢结构施工测量技术研究与实践[J].施工技术,2006,35:126-129.
  • 4沈里强 万里程 龙正武 等.国家体育场钢结构桁架拼装施工测量.施工技术,2006,35:142-145.