摘要
针对上海港国际客运中心客运综合大楼基坑面积大、工期紧、环境条件复杂等问题,通过调查研究和方案优化,在实施过程中采取相应的施工技术措施,在80日内顺利完成23万m3土方的开挖,为在黄浦江沿岸同类工程的施工提供了经验。
In the light of larger foundation pit, shorter construction deadline and complex envi- ronmental condition of synthetic building of Shanghai Port international Cruise Terminal, some construction measures were adopted to insure excavation security through elaborated survey and optimization. Successful earthwork of 230 thousand cubic meters within 80 days provides experience for similar engineering along Huangpu River in the future.
出处
《上海建设科技》
2007年第3期26-28,共3页
Shanghai Construction Science & Technology
关键词
深基坑
开挖
围护系统
阻水结构
黄浦江
deep foundation pit excavation enclosure system water-stop structure Huangpu River