人工挖孔桩穿过特殊地层时,往往是施工难度增大,工程进度受到影响,甚至会产生安全隐患,故而结合工程实例,分析了桩基施工过程中所出现的问题,提出了具体施工处理方法.工程实践证明,合理混合使用人工挖孔桩和冲击成孔灌注桩两种施工方法,缩短了工期,减少了基础的工程费用.
When carrying out manually--drilling of pile holes, special stratum usually exerts an obstacle to construction, which will slow down the construction progress and even cause some potential dangers. Combined with example analysis of practical construction, this paper is to analyze the problems occurred in the construction process of pile foundation, and work out concrete solutions to practical construction. It has been proven through practice that the alternate use of the technique of both manually--drilling and percussion drilling is effective in shortening the construction process and saving construction cost on foundation.
作者
孙彦
SUN Yan (Xuzhou Institute of Technology, Xuzhou 221008, China)
出处
《徐州工程学院学报》
2007年第4期70-72,共3页
Journal of Xuzhou Istitute of Technology
关键词
岩溶地基
地下水
冲击钻孔桩
人工挖孔桩
karst stratum foundation
groundwater
percussion drilled pile
manually--drilled pile