摘要
伊朗塔里干水利枢纽溢洪道工程泄槽底板混凝土浇筑,采用跨度17.1 m无轨面板滑模施工,取得了很好的效果,该滑模设计和施工特点,可供同类工程借鉴。
The spillway chute invert of Taleghan dam and HPP project in Iran is poured with concrete, with a span of 17. lm. The slipform construction has achieved excellent effect by applying railless on the invert. The slipform design and construction features will provide reference for similar projects.
出处
《西北水电》
2007年第2期41-43,47,共4页
Northwest Hydropower