摘要
喜河水电站施工时段短,强度高,工期控制突出,以及汉江洪水峰高量大、陡的特点,优化施工方案,采取分期导流,施工新技术、新措施,加快施工进度了使电站于2006年6月30日第一台机组提前半年并网发电。
The construction time of Xihe hydropower station was short with high intensity, and the flood of the Hanjiang River had the features of large peak flow with sharp hydrographs, so that the construction schedule might be controlled strictly. The optimal construction scheme was adopted, consisting of flow diversion by stages, use of new construction technology and new measures, by which the construction was speeded up and made the first set of generator put into operation ahead of schedule half a year.
作者
赵五一
ZHAO Wu - yi (China Hydropower Construction Consulting Company, Beijing Division, Beijing 100024, China)
出处
《西北水力发电》
2007年第3期66-67,77,共3页
Journal of Northwest Hydroelectric Power
关键词
施工方案
分期导流
施工进度
喜河水电站
construction scheme
flow diversion by stages
construction schedule