摘要
简要介绍新疆某电厂强夯及强夯置换地基处理试验方案的设计及试验过程,根据试验结果对地基处理方案进行了分析评价。
In this article, the design and execution process of dynamic compaction & dynamic replacement test of some electric power plant in Xinjiang is introduced, and based on the result of test, the ground treatment project is evaluated.
出处
《电力勘测设计》
2007年第3期10-13,共4页
Electric Power Survey & Design
关键词
强夯
强夯置换
湿陷性
dynamic compaction
dynamic replacement