厦门海底隧道风化深槽全断面帷幕注浆方案设计 被引量:15

Full-face Curtain Grouting for the Weathered Ditch in the Construction of Sea Tunnel in Xiamen
下载PDF
导出
摘要 厦门翔安海底隧道海底段穿越F1、F2、F3三处全强风化深槽和F4风化囊,风化深槽地段围岩破碎,岩体强度低,水压大,自稳能力差,在极端地质条件下存在发生渗透破坏的可能,施工风险极大。为确保隧道安全通顺利通过风化深槽、防止涌突水,对风化槽地段采用全断面帷幕注浆技术加固围岩,就全断面帷幕注浆技术参数确定、施工工艺和施工方法进行论述。 The under-the sea part of Xiang'an Tunnel in Xiamen goes through thoroughly weathered ditches at F1, F2 and F3, and a weathered sag areaat F4. The rock at the weathered ditches is fractured and weak with high water pressure and low stability, subject to the possibility of seepage and breakage under extreme geological conditions, presenting very high risks to the tunnel construction. In order to make the tunnel go through the ditches safely and prevent water burst, full face curtain grouting is adopted to strengthen the rock. This paper explains the determination of parameters and construction technology and methods for the full face curtain grouting.
作者 胡文涛
出处 《石家庄铁道学院学报》 2007年第2期130-134,共5页 Journal of Shijiazhuang Railway Institute
关键词 帷幕注浆 风化槽 注浆加固 海底隧道 curtain grouting weathered ditch grouting sea tunnel
  • 相关文献

参考文献2

  • 1持田丰 汪景俊 译.青函隧道的破碎带的稳定处理.隧道译丛,1978,(6):14-25.
  • 2佐腾昭 汪景俊 译.青函隧道超前导洞F-1断层的突破.隧道译丛,1989,(9):64-65.

共引文献5

同被引文献123

引证文献15

二级引证文献148

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部