摘要
结合具体工程实践,介绍了盾构掘进工艺的施工工序,并从盾构机分体始发、江底掘进和曲线段施工等方面论述了工程的重点及难点控制,为城市地铁盾构施工合理使用土地,分体始发掘进提供了施工技术经验。
Combined with concrete practice, it introduces the constructing sequence of shield shaped digging crafts. Started from sub-units of shield shaped machines, river-bottom digging, curve construction, it discusses the key points and difficulties in project control, offers constructing experience for rational usage of land and independent digging of shield shaped digging construction.
出处
《山西建筑》
2007年第20期310-311,共2页
Shanxi Architecture
关键词
盾构施工
地铁
盾构机
涌水量
shield shaped construction, subway, shield shaped machines, water-pouring amount