摘要
通过对三峡工程GJ围堰A区高喷墙渗漏原因的分析,提出了两个切实可行的治理方案。
By analysis of the leakage of high-pressure grouting wall of area A of GJ weir of the Three-Gorge project, two availabel control measures are put forward. The test shows reinforcing high-grouting is successful.
出处
《西部探矿工程》
CAS
1997年第1期6-7,共2页
West-China Exploration Engineering