摘要
通过广州沙园站广佛线与8号线换乘的地铁车站工程设计实例,研究和分析了重叠式换乘站车站客流量、客流组织中的换乘方式选择。在选定平行换乘方式时,对公共区扶梯的5种布置方式进行了分析探讨。最后提出了一种直达地下三层的扶梯设于沿8号线侧的两端部方案。这是一种较合理、经济、适用的布置方式。
Through the design of the subway station,Shayuan Station,the transfer station between Line Guangfo and Line 8 in Guangzhou,the choice of the transfer form according to the passenger flow volume and its organization of the overlaid transfer station was researched and analyzed.When choosing the parallel transfer method,the 5 installment types of the escalator in public area were discussed.Finally,the plan of the escalator(through to B3) being installed at the 2 ends of Line 8 was applied,which should be a relatively rational,economical and suitable installment type.