考虑高面板坝堆石体的流变变形效应对堆石体的最优施工碾压进度方案进行了研究。结果表明,堆石体的本身流变变形特性对不同施工碾压进度方案下的面板垫层变形影响较大。堆石坝不同材料分区的特点从客观上决定了高堆石坝必然存在一个较优的施工填筑上升方案。堆石体均匀上升的填筑进度方案的面板垫层法向最大位移较小,且沿面板坡向的分布比较均匀,对面板与垫层间的协调变形有利。从最优填筑方案的角度来看,建议高堆石坝采用均匀上升的碾压施工程序。
Optimal construction scheme of high concrete face rockfill dam(CFRD) is studied taking into account creep deformation of rock.fill. The results show that creep characteristic of rockfill influence on deformation of dam bedding node under different construction schemes. The zone by zone character of various materials of a rockfill dam decides objectively the necessary existence of an optimal scheme for the construction of filling ascension works. The maximum normal displacement of the facial slab is small in the filling. Scheme where the rock-filling body ascends uniformly and its distribution along the slab slope is also rather uniform, which is favourable to the harmony between the deformations of slab and pad layer beneath it. From the view of the majorized filling scheme, it is suggested that the rolling and compacting construction procedure producing uniform ascension of filling shall be used for high rockfill dams.
出处
《岩土力学》
EI
CAS
CSCD
北大核心
2007年第7期1465-1468,共4页
Rock and Soil Mechanics
基金
国家自然科学基金资助项目(No.50509019)
关键词
面板堆石坝
流变
施工程序
有限元
仿真分析
concrete face rockfill dam
creep
construction process
FEM