以云南省盈江县朗外河电站引水隧洞工程的施工为实践基础,就水工隧洞塌方产生的原因进行分析,并重点从施工过程方面对水工隧洞塌方的预防作简要的阐述.
The reason of the landslide of hydraulic tunnels is analyzed by the example of the water tunnel construction of Langwaihe hydropower station in Yingjiang county of Yunnan province. Based on the construction course, the landslide protection of hydraulic tunnels is stated.
出处
《江西水利科技》
2007年第2期103-107,共5页
Jiangxi Hydraulic Science & Technology
关键词
水工隧洞
塌方
原因
预防
Hydraulic tunnel
Landslide
Reason
Protection