摘要
结合实船下水的测试结果,对测试项目的核心问题——平衡梁受力测试进行了分析,提出了下水过程测试各项目间必须同步,才能提高测试结果的可靠性;论述了电阻应变测量法测试的步骤和方法.通过试验,证实了用较小船台可建造较大船舶.
In combination with the measurement results of factual vessel launching,this paper makes an analysis on the core of measurement items measurement of forces on the balance beam.Steps and methods of RSM (Resistance Strain Measurement) are stated and the possibility for setting up larger versels with a smaller ship way is verified.
出处
《武汉交通科技大学学报》
EI
1997年第2期211-215,共5页
Journal of Wuhan University of Technology(Transportation Science & Engineering)
关键词
平衡梁
下水
测量
船舶
受力
电阻应变测量法
ship way
balance beam
launching
RSM (Resistance Strain Measurement)