摘要
提出火力发电厂大容量输煤系统火车卸车设施较为常用的3个设计方案,对3个设计方案的主要特点、适用条件进行了详细论述,并以华阳鄂尔多斯电厂2×660MW火电机组工程为例,对3个设计方案进行了技术经济比较。在此基础上,提出大容量输煤系统火车卸车设施的设计建议。
This paper presents three design schemes of train unloading facility in large capacity coal conveying system in coal fired power plants. In this paper, detailed dissertations are made on the major characteristics and applicable conditions of three design schemes, and technical-economical comparisons are also made for the three design schemes taking the example of Huangyang Erodes Power Plant of 2 × 660 MW units. Finally, suggestions are put forward on the above basis for the design of train unloading facility in large capacity coal conveying system.
出处
《水利电力机械》
2007年第6期1-8,共8页
Water Conservancy & Electric Power Machinery
关键词
大容量
输煤系统
火车卸车设施
方案研究
large capacity
coal conveying system
train unloading facility
scheme study