通过一台1000 MW大型氢冷发电机定子线棒端部漏氢修复后的试验实例,总结了验证修复效果的各项试验准备、实施、数据分析及注意事项,提出了一些新颖、实用的试验手段。
Besed on the experience, gained of repairing hydrogen leakage defects of stator winding, of a large 1 000 MW hydrogen cooled generator, the procedure of check-testing the outcome of the repair work is being summarized, including preparations required, tests to be performed, and data analysis, accompanied by points to be observed. Some of the mentioned means of testing are inventive and practical.
出处
《发电设备》
2007年第4期312-315,共4页
Power Equipment
关键词
能源与动力工程
发电机
定子线棒
漏氢
试验
energy and power engineering
generator
stator conductor bar
hydrogen leakage