摘要
通过介绍青岛东亿供热中心58 MW热水锅炉钢架的安装,对锅炉钢架在场地狭窄、工期紧张的情况下,组织钢架分片组合焊接和吊装技术作了详细阐述,从而论证了钢架组合焊接和吊装技术不仅是行之有效的,而且为日后类似工程提供了保证.
The article introduces the installment of Qingdao Dongyi Heating Center 58MW hot water boiler, and mainly discusses the technology of fixing steel frame lamination combination welding and hoisting under the condition of the narrow place. It proves that the technology of the steel frame combination welding and hoisting is an effective measure of lessening vibration, moreover it will guarantee the similar project in the future.
出处
《青岛理工大学学报》
CAS
2007年第3期130-133,共4页
Journal of Qingdao University of Technology
关键词
锅炉钢架
组合吊装
方案选择
boiler steel frame
combination hoisting
plan choice