介绍了泰安抽水蓄能电站上水库库盆采用的土工膜水平防渗措施及其施工缺陷处理,并对水库初期蓄水中的渗漏情况进行了简要的分析。
This paper introduced the geomembrane horizontal seepage prevention measures at the upper reservoir basin at Tai'an pumped storage power station, as well as treatments to construction defects. Further more, the seepage in the beginning impounding period was analysed.
出处
《大坝与安全》
2007年第3期36-38,48,共4页
Dam & Safety
关键词
泰安抽水蓄能电站
土工膜
防渗
效果
Tai'an pumped storage power station
geomembrane
seepage prevention
effect