错峰控制中兼顾双目标的断电模型分析

Novel Model of Power Terminate Plan Considering Two Object in Peak Load Shifting Control
下载PDF
导出
摘要 提出了一种同时考虑居民不满意度和断电经济损失的错峰控制短期断电计划的多目标新模型。首先构造了居民的不满意度函数,其次,对两个单目标确定性模型求解得到目标函数值;最后,对目标值进行一定程度的伸缩,采用非线性规划方法求解,得到新的工业区以及居民区断电情况。仿真结果表明,提出的新策略在各自单目标优化值轻微伸缩的情况下使双目标综合考虑效果更好,该策略对可持续发展战略和错峰控制限电分配中多因素公平性有重要现实意义。 A novel multi-objective optimal short-term power terminates planning in a power system was proposed. Both dissatisfaction degree of dwellers and economic loss were considered in this model. At first, the dissatisfaction degree function of dwellers was constructed; secondly, each single-objective deterministic model was solved so that its objective value was obtained along with the results of unit commitment and power dispatch; finally, the multi-objective programming problem was reformulated into nonlinear Single objective programming problem so as to get the power limiting distribution of each zone. The numerical results demonstrate that the scheme obtained from the multi-objective model can meet functions better than that obtained from the single-objective deterministic model with slight variation in the every single-objective. This method of decision making is significant for sustainable development strategy and the multi-factor justice of power limiting distribution for peak load shifting control planning.
出处 《系统仿真学报》 EI CAS CSCD 北大核心 2007年第15期3534-3539,共6页 Journal of System Simulation
基金 国家自然科学基金项目(60274099) 教育部博士点基金项目(20020145007)
关键词 多目标 不满意度 错峰控制 限电分配 multi-objective dissatisfaction degree peak load shifting control power limiting distribution
  • 相关文献

参考文献11

  • 1邓树林.“电荒”为哪般?[J].今日中国,2004,53(2):55-58. 被引量:1
  • 2徐仁武.迎峰度夏激励政策及实施机制研究[J].电力需求侧管理,2004,6(3):16-19. 被引量:2
  • 3刘升,邱向京,陈维烈,魏宏俊.多措并举缓解电力供需紧张矛盾[J].电力需求侧管理,2005,7(1):53-54. 被引量:20
  • 4Ahmed Shamsuddin.Seasonal models of peak electric load demand[J].Technological Forecasting and Social Change (S0040-1625),2005,72(5):609-622.
  • 5Al-Shakrchi M R G,Ghulaim M M.Short term load forecasting for Baghdad electricity region[J].Electr.Mach.Power Syst (S0731-356X),2000,28(3):355-371.
  • 6Senjyu T,Sakihara H,Tamaki Y,Uezato K.Next day peak load forecasting using neural network with adaptive learning algorithm based on similarity[J].Electr.Mach.Power Syst (S0731-356X),2000,28(6):613-624.
  • 7Delgado M,Herrera F,Herrera Viedma E,et al.Combining numerical and linguistic information in group decision making[J].Information Sciences (S0020-0255),1998,10(7) 177-194.
  • 8Chiclana F,Herrera F,Herrera Viedma E.Integrating three representation models in fuzzy multipurpose decision making based on fuzzy preference relations[J].Fuzzy Sets and Systems (S0165-0114).1998,9(7):33-48.
  • 9Bryson Noel,Mobolurin Ayodele.An action learning evaluation procedure for multiple criteria decision making problems[J].European Journal of Operational Research (S0377-2217),1999,9(6):379-386.
  • 10Hawng C L,Yoon K.Multiple attribute decision making[M].Berlin,Heidelberg,New York:SpringerVerlag,1981:1-107.

二级参考文献3

  • 1朱成章 徐仁武.需求侧管理[M].北京:中国电力出版社,1998..
  • 2国家电力公司电力营销培训教材编委会.电力市场营销[M].北京:中国电力出版社,2000..
  • 3The Load Management of Pacific Gas and Electricity Corporation [EB/OL] .http://www.pge.com, 2004-02-18.

共引文献19

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部