上海京银大厦裙房预应力转换梁加固设计 被引量:2

Retrofitting Design of Prestressed Transfer Beam of Shanghai Jingyin Building Annex
下载PDF
导出
摘要 上海京银大厦裙房框架柱柱距8.20m,因使用功能改变需将底层两根中柱拔除,使框架梁跨度增加一倍。经方案比较,采用了预应力转换梁加固技术,介绍了预应力加固设计方法和构造措施,并对拔柱过程进行了测试。测试结果表明,工程的加固设计方法和施工措施正确,满足规范要求。 The frame column bay of Shanghai Jingyin Building annex is 8.20m. Two middle columns on the first floor are needed to be taken-out due to the changing of service function, therefore the frame span becomes twice. Through the comparison of the retrofitting plans, the retrofitting technique of prestressing transfer beam is adopted. The prestressed design method and detail measures are introduced. Execution test on taking-out column process is conducted. The test results show that the retrofitting design method and construction measures on this project are successful.
作者 张德锋
出处 《建筑结构》 CSCD 北大核心 2007年第7期69-71,37,共4页 Building Structure
关键词 预应力 加固设计 施工测试 prestressing retrofitting design execution test
  • 相关文献

参考文献2

二级参考文献1

共引文献6

同被引文献7

引证文献2

二级引证文献5

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部