摘要 厦门港招银港区7#泊位建设过程中基床爆夯拟通过试夯,以确定基床爆夯参数。试夯主要综合考虑了水流、周围建筑物及炸药性能等因素,通过计算数据和试验数据比较分析,寻找适合爆夯施工的单包炸药配重、炸药单包重量、药包布设网格间距及爆夯遍数等参数,最终完成该泊位抛石基床爆夯施工。 The parameters of explosive compaction for base-bed during the construction of Berth 7tth wharf Engineering, Harbour Area of China Merchants Bank,Xiamen Port, are determined through test explosive compact. The factors such as water flow, ambient structure and performance of powder are mainly and comprehensively considered in the test. The parameters of counterweight, weight of each explosion bag,the gird spacing and the times of explosive compaction suitable for explosive compaction construction are seek by the comparison and analysis of test data.
作者 王树
出处 《港工技术》 北大核心 2007年第4期46-48,共3页 Port Engineering Technology
关键词 水工工程 抛石基床 爆夯 技术参数 water engineering throwing rock base-bed explosive compaction technical parameter
  • 相关文献

参考文献6

  • 1JTJ/T258—98,爆破法处理水下地基和基础技术规程[S].
  • 2GB6722—2003.爆破安全规程[S].[S].,..
  • 3JTJ286,水运工程爆破技术规范[S].
  • 4JTJ221—98.港口工程质量检验评定标准[S].[S].,..
  • 5JTJ290-98.重力式码头设计与施工规范[S].[S].,..
  • 6JTJ250—98.港口工程地基规范[S].[S].,..

共引文献60

同被引文献1

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部