摘要
介绍某工程采用多桩型复合地基的方案选择、设计方法,以及采用碎石桩和CFG桩复合地基进行处理的加固效果,消除液化、震陷和场地不均匀性,提高地基承载力,控制变形。
In order to eliminate liquefaction, seismic settlement and soil unevenness, combined with a project, the scheme selection and design methods of multi-pile composite foundation are introduced to improve bearing capacity and reduce settlement. The effect of treatment for foundation applied in the project is also presented.
出处
《施工技术》
CAS
北大核心
2007年第8期17-18,40,共3页
Construction Technology
关键词
碎石桩
CFG桩
复合地基
液化
gravel pile
CFG pile
composite foundation
liquefaction