期刊文献+

浅析瀑布沟水电站地下厂房系统洞室群围岩变形 被引量:3

Surrounding Rock Deformation of Caverns in Underground Powerhouse Complex at Pubugou Hydropower Station
下载PDF
导出
摘要 瀑布沟水电站地下厂房系统洞室群由于地应力高,开挖时围岩变形大,施工中曾多次发生岩爆,对围岩稳定造成了不利影响。通过对施工期围岩变形监测进行分析研究,为地下洞室的开挖、支护及稳定性评价提供了一些可借鉴的经验。 During excavation of caverns in underground powerhouse complex at Pubugou hydropower station,surrounding rock deformed greatly and rock burst occurred many times during construction due to high in-situ stress,leading to unfavorable effects on surrounding rock stability.Analysis and study are performed for surrounding rock deformation monitoring during construction and analysis results are presented to provide references for excavation,support and stability assessment of underground caverns.
出处 《四川水力发电》 2007年第4期68-70,共3页 Sichuan Hydropower
关键词 高边墙 高地应力 变形监测 围岩变形 地下厂房 瀑布沟水电站 high slope high in-situ stress deformation monitoring surrounding rock deformation underground powerhouse Pubugou hydropower station
  • 相关文献

同被引文献44

引证文献3

二级引证文献84

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部